Facility Management Office for the Distribution of international Fisheries Products

Busan International Fish Market

History(1995~2008 year)
2008 2008.04 Completion of Busan International Fish Market
2007 2007.10 Opening of Management Office
2007.08 Establishment of Operation Management Plan of Busan International Fish Market
2007.04 Holding of Gamcheon Wholesale Market Promotion Situation Report Meeting (Under the presidency of the Mayor, 91 persons)
2007.03 Inauguration of T/F Team(5 persons)
2006 2006.12 Organization and Operation of Opening Preparation Committee
2006.10 Execution of Review and Inspection of Treated Amount of Materials(Busan City)
2006.08 Holding of Presentation Meeting for Opening Preparation Plan (Seoul and Busan, Two Times)
2006.07 Establishment of Basic Preparation Plan
2005 2005.12 Services for Creation and Revitalization Plan of Gamcheon Port International Fisheries Distribution Trade Base(The Ministry of Maritime Affairs and Fisheries)
2003 2003.11 Completion of Services for Efficient Management & Operation Plan of Wholesale Market(Busan City)
2001 2001.10 Completion of Each Administrative Procedure Related to the Construction Work (Harbor Construction Work by Non-Management Office, etc.)
2000 2000.12 Ground-Breaking Ceremony(About 2,000 persons including the Prime Minister, The Minister of Maritime Affairs and Fisheries and the Mayor, etc. Participated)
2000.07 Selection of Consortium of Daewoo Construction Co., Ltd.
2000.03 Notice of Turnkey for Execution Design
2000.02 Completion of Basic Design Service
1997 1997.04 Decision as State Support Project and Security of Site
※ Working Expenses Support 1998 Year
1995 1995.06 Completion of Basic Plan Service

Advanced Seafood Processing Complex in Busan

History(2008~2014 year)
2014 2014.02 opening ceremony(on Feb 21).
2013 2013.07 The construction of the Complex is completed (on July 31). Operation Management of Advanced Complex of Processed Seafoods (on July 10).
2013.01 The plan for operation of the Complex is prepared.
2012 2012.02 The first work (for reclamation) is completed.
2011 2011.10 The explanation meeting on the construction of the Complex is made to Seafood processors.
2011.06 The official work starts.
2011.03 A construction permit is issued by Seo-gu Office.
2010 2010.12 The actual plan for work at the port is approved.
2010.10 Opening ceremony is conducted.
2010.06 The permit is allowed for the construction of non-controlled port work.
2010.05.10 / 05.19 The contract is made for first work and the work starts.
2010.03 Daewoo E&C consortium is selected as a proper designer.
2010.03~12

The environmental impact assessment is conducted and the coordination with related authorities is completed.

  • The future accident impact is reviewed
  • The traffic impact is analyzed and the actions for improving the traffic are taken
  • The cultural remains are researched
  • The environmental impact is assessed
2009 2009.11 The basic plan service is completed.
2008 2008.07 ~ 2009.03 The basic plan service is completed.